"We view this as a positive development both for our company and Mirant," says Gary G. Ely, chairman of Avista. "We will retain a significant portion of this important generation project in addition to working with Mirant."
As co-owners of the plant, Mirant and Avista will share equally in all construction and operating costs. To date, Avista has $140 million invested in construction, which is estimated to cost between $180 million and $190 million when completed. Additionally, the two firms will work jointly in marketing the plant's power production.
When completed, the combined-cycle power plant will be interconnected to the Bonneville Power Administration's transmission system and near the Stanfield natural gas hub.
If all goes according to plan, the sale is expected to close during the fourth quarter of the year, pending regulatory approval.
Want to continue reading?
Become a Free ALM Digital Reader.
Once you are an ALM Digital Member, you’ll receive:
- Breaking commercial real estate news and analysis, on-site and via our newsletters and custom alerts
- Educational webcasts, white papers, and ebooks from industry thought leaders
- Critical coverage of the property casualty insurance and financial advisory markets on our other ALM sites, PropertyCasualty360 and ThinkAdvisor
Already have an account? Sign In Now
*May exclude premium content© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.