The 8,000 sf facility includes three operating rooms, patient rooms, common areas, office space and a parking lot. Symbion moved in Jan. 9. The project was built at a development cost of $178.75 per sf.
The center passed North Carolina's final inspection lst week. The project was completed on time and on budget, the company says in a prepared statement.
Want to continue reading?
Become a Free ALM Digital Reader.
Once you are an ALM Digital Member, you’ll receive:
- Breaking commercial real estate news and analysis, on-site and via our newsletters and custom alerts
- Educational webcasts, white papers, and ebooks from industry thought leaders
- Critical coverage of the property casualty insurance and financial advisory markets on our other ALM sites, PropertyCasualty360 and ThinkAdvisor
Already have an account? Sign In Now
*May exclude premium content© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.