SAN DIEGO—A record 83% of multifamily developer respondents reported construction delays in the jurisdictions where they operate, according to the seventh edition of the National Multifamily Housing Council (NMHC) COVID-19 Construction Survey. NMHC released the survey during its annual conference here in San Diego, where housing stability and rental assistance were also topics of discussion as GlobeSt.com previously reported.
Of this group, 80% reported experiencing delays in permitting, up slightly from the 77% in round six and comparable to the results seen in the earlier rounds. Survey respondents reporting construction delays also indicated a significant pause in starts, with a similar 80% still reporting delayed starts over one year into the pandemic.
The main reasons cited for delays in starts were permitting, entitlement, and professional services (70%); projects not being economically feasible at this time (56%); and economic uncertainty (27%). The percentage of responses attributing delays to projects not being economically feasible at this time increased from 30% in round six to 56% this round.
Want to continue reading?
Become a Free ALM Digital Reader.
Once you are an ALM Digital Member, you’ll receive:
- Breaking commercial real estate news and analysis, on-site and via our newsletters and custom alerts
- Educational webcasts, white papers, and ebooks from industry thought leaders
- Critical coverage of the property casualty insurance and financial advisory markets on our other ALM sites, PropertyCasualty360 and ThinkAdvisor
Already have an account? Sign In Now
*May exclude premium content© 2024 ALM Global, LLC, All Rights Reserved. Request academic re-use from www.copyright.com. All other uses, submit a request to [email protected]. For more information visit Asset & Logo Licensing.