Thought Leader Presented by Partner Engineering & Science, Inc.

Reducing Construction Risk from Cost and Supply Chain Issues

With the U.S. economy ramping up, the demand for materials such as steel and lumber has quickly outpaced its supply resulting in an extraordinary supply chain event. Help mitigate the risk of delays and cost increases both before and after construction commencement with these tips.

It’s true. All we hear about today is about the record high materials price increases. With the U.S economy ramping up, the demand for materials such as steel and lumber has quickly outpaced its supply. Now let’s add to that the tariffs placed on the imports of products like steel that are eliminating the ability to be competitive. It’s no secret construction costs for projects will be going up if materials orders haven’t been secured.

Unfortunately, that isn’t where the construction risk ends. A domino effect from having too little supply has resulted in an extraordinary supply chain event for contractors and vendors alike. Not only are the materials more costly, but the lead times for both the fabrication and delivery have become severely impacted. Construction projects are now at high risk of going both over budget and beyond schedule, and this is not expected to be resolved over the next few months, but will last at least for the balance of the contracts in progress and those being entered into now.

So, what can you do? It’s really all about doing your due diligence: being very thorough and hyper aware of the all elements of your project and the current economic climate. Below you will find some suggestions on how to do this during both the pre-closing and post-closing of construction loans.

.

PRE-CLOSING OF CONSTRUCTION LOANS

Document and Cost Reviews. A thorough third-party review of all project documents is crucial, especially the review of the construction contracts including the attached assumptions and clarifications. Lenders and investors need to understand the basis of the construction contract and not assume that they are okay just because it is already signed. Paying particular attention to the following items can help mitigate risk:

Contractor Evaluations. Now more than ever, any investor or lender looking to build and finance a project really needs to dive deep into evaluating the contractor, the contractor’s team, and the developer to fully qualify them. It goes beyond just looking at the contractor’s qualifications and prior experience. A thorough third-party underwriting job must be done to vet the contractor. A diligent review of the contractor, with special attention to the following items, is critical:

POST-CLOSING OF CONSTRUCTION LOANS

Communication. First and foremost, prior to and during construction commencement there should a high level of open and honest communication between all parties (lenders, developers, contractors, and third-party consultants). Early identification of problems allows the entire team to work to resolve the problems before they become more difficult to solve.

Construction Progress Monitoring. Regular updates on the progress of any construction project is important. However, the current climate of cost and supply chain issues necessitates even more thorough third-party reporting. Knowing the project’s conformance to the schedule, assessing the material and workmanship adequacy, verifying the appropriateness of the contractor’s pay application, and identifying construction changes (even potential or pending change orders) are the bare minimums of a good status report. Consultants need to be vigilant and keep in regular communication, with special regard to the following items:

Funds Control / Funds Disbursement. Although typically done in conjunction with construction progress monitoring, funds control is an excellent tool to prevent mismanagement of project funds. It assures that funds are being approved according to actual work completed, that errors or discrepancies in payment requests are caught, that lien waivers are collected, and that change orders are being tracked. Most importantly, it ensures that funds are being given to the appropriate parties and not being diverted to other financially stressed projects the contractor may be working on. Since projects now may require a high level of up-front deposits and pre-payments, risk is elevated for lenders and investors, which warrants a careful review of project accounting.

Substitute Materials. Contractors should keep in communication with vendors about system warranties that require the use of their branded parts. Due to uncertainty of product availability, some manufacturers are allowing other manufacturers to provide parts like fasteners to complete a system while still honoring their warranty. Any substitutions should be reviewed by the designers of record to confirm conformance with the original design and required warranties.

************

Although today’s contractors are expected to fully understand the challenges of the market, many practices and processes are now being done differently than they were a year ago. There will always be some degree of resource and supply chain issues, but investors, lenders, and contractors alike are having to reevaluate how they look at risk. Diligent risk management practices, clear communication among all parties, and a thorough understanding of all aspects of a construction project are necessary to mitigate the increased risks of today’s economic climate and its impacts over the full term of construction projects.